Progress
Construction of new amenities for Barrenjoey Headland started in early July 2024. Work is progressing well. Earthworks were completed in July and August.
In early September, concrete for the footings and slab of the new building was flown in by helicopter. Plumbing services below the finished floor were completed, and the concrete slab is now done.
In late September, a helicopter operation transported concrete and materials for the walls and roof. With fine weather in September, the work program remains on track.
Visitor access during construction
Access to Barrenjoey Headland and the lighthouse will remain open during the construction period and access trail upgrade works. However, visitors may experience changes and restrictions, including the following:
- There will be increased vehicle movements to the headland and the lighthouse via the beach and service road.
- Pedestrian access will be retained throughout construction via Smugglers Track.
- The Barrenjoey access trail will be closed Monday to Friday to allow contractors to access the site and undertake maintenance work.
- There will be no visitor access to the south-eastern part of the lighthouse and below the Head Lightkeepers Cottage. This area will be fenced for construction and materials storage.
- There will be temporary closures of the headland or parts of it during helicopter operations to deliver materials (this is necessary to manage load limits on the access trail).
During construction, visitors can continue to use the temporary amenities, which will be removed when the permanent amenities are operational.
How do I find out more?
Are you planning to visit Barrenjoey Headland? Check current alerts for closures.
Please follow the directions of onsite signage and avoid entering fenced-off areas.
Information about Barrenjoey Headland amenities is available from the project webpage. Anyone can sign up to receive newsletters by visiting the project webpage.